Traffic lane in Köln
(DEGES) Umbau AD Heumar
Day 701
It was planned for 26 months.99 days left in the plan
No reports yet – be the first voice.
Traffic lane in Köln
Day 701
No reports yet – be the first voice.
One square per day since work began, based on reports from people on site.
Zeitraum dieser Bauphase: · Beginn: 22.11.24 um 15:00 Uhr · Ende: 31.01.27 um 15:00 Uhr · (Ende der Gesamtmaßnahme: 31.01.27) · A59: km 6.71 --> km 6.13 · Länge: 0.59 km | Maximale Durchfahrtsbreite: 5.85 m · (DEGES) Umbau AD Heumar
No approved photos yet.