Traffic lane in Neustadt an der Weinstraße

A65 Neustadt-Süd – Deidesheim

Day 55Day55

It was planned for 11 weeks.25 days left in the plan

No reports yet – be the first voice.

Baustellenindex

Every construction site gets a public counter. One tap on site is enough.

Explore

  • Map
  • Ranking
  • Add a site

Legal

  • Legal notice
  • Privacy
Instagram image

When work happened

One square per day since work began, based on reports from people on site.

MonTueWedThuFriSatSun
Sept
Oct
workedstandstillno reporttoday

Site sign

Responsible
City
Size
Traffic lane
Start
30/08/2026official
Planned end
17/11/202625 days left
Status
Active
Last report
never
Source
Autobahn GmbH
Absurdity score
4 / 100from duration, size, standstill and delay

Zeitraum dieser Bauphase: · Beginn: 30.08.26 um 00:00 Uhr · Ende: 02.11.26 um 00:00 Uhr · (Ende der Gesamtmaßnahme: 17.11.26) · A65: Landau -> Ludwigshafen, zwischen 3.5 km hinter AS Neustadt-Süd und 2.5 km vor AS Deidesheim · Länge: 0.63 km | Maximale Durchfahrtsbreite: 3.5 m · A65 Verkehrsführung für Bauwerks und Asphalt Sanierung

Date changes

  1. 23/10/2026End set to 17/11/2026