Traffic lane in Landkreis Freudenstadt

A81 Horb am Neckar – Rottenburg

Day 18Day18

It was planned for 5 weeks.18 days left in the plan

No reports yet – be the first voice.

Instagram image
Baustellenindex

Every construction site gets a public counter. One tap on site is enough.

Explore

  • Map
  • Ranking
  • Add a site

Legal

  • Legal notice
  • Privacy

When work happened

One square per day since work began, based on reports from people on site.

MonTueWedThuFriSatSun
Oct
workedstandstillno reporttoday

Site sign

Responsible
City
Size
Traffic lane
Start
06/10/2026official
Planned end
10/11/202618 days left
Status
Active
Last report
never
Source
Autobahn GmbH
Absurdity score
1 / 100from duration, size, standstill and delay

Zeitraum dieser Bauphase: · Beginn: 06.10.26 um 09:00 Uhr · Ende: 10.11.26 um 18:00 Uhr · (Ende der Gesamtmaßnahme: 10.11.26) · A81: Singen -> Stuttgart, zwischen 1.1 km hinter AS Horb am Neckar und 7.1 km vor AS Rottenburg · Länge: 2.72 km | Maximale Durchfahrtsbreite: 5.85 m · A81 Neckartalbrücke_Instandsetzung Belag_FR Stgt.

Date changes

  1. 23/10/2026End set to 10/11/2026