A7 Northeim-Nord – Am Bierberg

Day 8Day8

It was planned for 7 months.205 days left in the plan

No reports yet – be the first voice.

Baustellenindex

Every construction site gets a public counter. One tap on site is enough.

Explore

  • Map
  • Ranking
  • Add a site

Legal

  • Legal notice
  • Privacy
Instagram image

When work happened

One square per day since work began, based on reports from people on site.

MonTueWedThuFriSatSun
Oct
workedstandstillno reporttoday

Site sign

Responsible
City
Size
Traffic lane
Start
17/10/2026official
Planned end
17/05/2027206 days left
Status
Active
Last report
never
Source
Autobahn GmbHOfficial list
Absurdity score
7 / 100Provisional: so far based only on duration and planned dates.

Zeitraum dieser Bauphase: · Beginn: 17.10.26 um 05:00 Uhr · Ende: 17.05.27 um 20:00 Uhr · (Ende der Gesamtmaßnahme: 17.05.27) · A7: Kassel -> Hannover, zwischen 5.0 km hinter AS Northeim-Nord und 0.2 km vor Am Bierberg · Länge: 1.99 km | Maximale Durchfahrtsbreite: 10.25 m · Via Erhalt A7 von Echte (AS) nach Northeim-Nord (AS) Brückenneubau BW 2060

Date changes

  1. 23/10/2026End set to 17/05/2027