Traffic lane in Landkreis Vorpommern-Greifswald

GST, A20, AS Jarmen (RF Stettin ), Windpark Völschow

Day 25Day25

It was planned for 7 weeks.21 days left in the plan

No reports yet – be the first voice.

Baustellenindex

Every construction site gets a public counter. One tap on site is enough.

Explore

  • Map
  • Ranking
  • Add a site

Legal

  • Legal notice
  • Privacy
Instagram image

When work happened

One square per day since work began, based on reports from people on site.

MonTueWedThuFriSatSun
Oct
workedstandstillno reporttoday

Site sign

Responsible
City
Size
Traffic lane
Start
29/09/2026official
Planned end
14/11/202622 days left
Status
Active
Last report
never
Source
Autobahn GmbH
Absurdity score
2 / 100from duration, size, standstill and delay

Zeitraum dieser Bauphase: · Beginn: 29.09.26 um 22:00 Uhr · Ende: 14.11.26 um 00:00 Uhr · (Ende der Gesamtmaßnahme: 14.11.26) · Von A20: Rostock -> Stettin, zwischen 4.3 km hinter AS Gützkow und Demminer Land nach Abfahrt von der A20: AS Jarmen (aus Richtung Gützkow) · Länge: 0.52 km | Maximale Durchfahrtsbreite: 4.5 m · GST, A20, AS Jarmen (RF Stettin ), Windpark Völschow

Date changes

  1. 23/10/2026End set to 14/11/2026