Traffic lane in Landkreis Bernkastel-Wittlich

A60 Erneuerung der Fahrbahn, Bau der Mittelstreifenüberfahrt

Day 5Day5

It was planned for 12 days.7 days left in the plan

No reports yet – be the first voice.

Baustellenindex

Every construction site gets a public counter. One tap on site is enough.

Explore

  • Map
  • Ranking
  • Add a site

Legal

  • Legal notice
  • Privacy
Instagram image

When work happened

One square per day since work began, based on reports from people on site.

MonTueWedThuFriSatSun
Oct
workedstandstillno reporttoday

Site sign

Responsible
City
Size
Traffic lane
Start
19/10/2026official
Planned end
31/10/20268 days left
Status
Active
Last report
never
Source
Autobahn GmbH
Absurdity score
0 / 100from duration, size, standstill and delay

Zeitraum dieser Bauphase: · Beginn: 19.10.26 um 16:00 Uhr · Ende: 31.10.26 um 00:00 Uhr · (Ende der Gesamtmaßnahme: 31.10.26) · A60: km 67.06 --> km 66.10 · Länge: 0.96 km | Maximale Durchfahrtsbreite: 3.5 m · A60 Erneuerung der Fahrbahn, Bau der Mittelstreifenüberfahrt

Date changes

  1. 23/10/2026End set to 31/10/2026